MANILA, Philippines — The Metropolitan Manila Development Authority (MMDA) has proposed the construction of rainwater impounding facilities inside Camp Aguinaldo to ease recurring flooding along EDSA, with the proposed design released on Wednesday., This news data comes from:http://gyglfs.com
The plan calls for detention ponds that will temporarily store excess rainwater during downpours and gradually release it into the EDSA drainage system leading to Makiling Creek.
According to the proposal, the project will be implemented in three phases covering 182 hectares: a golf course near Gate 2, another near Gates 3 and 4, and an open space near Gate 6.
For the first phase near Gate 2, the detention pond has a 361-meter perimeter, a 4,650-square-meter area, an 8-meter depth, and a 37,200-cubic-meter capacity, designed for a 25-year return period (15.6 mm/hr over 24 hours) and exceeding the needed 36,945 cubic meters.
MMDA’s schematic shows that under normal weather, water bypasses the pond and traverses the lagoon to EDSA; during heavy rains, floodgates divert flows into the pond; after rains, pumps discharge stored water slowly to EDSA toward Makiling Creek.
MMDA unveils plan to build rainwater impounding facilities in Camp Aguinaldo

The scope of work covers the impounding area, an operations and power house, drainage and electromechanical works, and landscaping and golf course restoration, with a treatment facility under consideration.
Officials said operations and maintenance arrangements and a memorandum of agreement were being discussed..
MMDA unveils plan to build rainwater impounding facilities in Camp Aguinaldo
- DPWH to revisit budget, to complete revisions within 2 weeks
- Discayas must return money before seeking immunity – Remulla
- Pagasa sees cyclone-free week across PH
- Cooperatives group lauds Konektadong Pinoy Law as milestone in digital inclusion
- Eala ousts Day, enters Guadalajara Open final
- Navotas inks deal for school feeding project
- Hope dwindles for survivors days after deadly Afghan quake
- House committee subpoenas Sarah Discaya, 4 other contractors over flood control project anomalies
- DSWD program reduced hunger
- Makati distributes Blu Card cash aid